Construction Resources | Oklahoma
					
					
												General Contractors
						 | 
												Subcontractors
						 | 
												Material Suppliers
					
					
					
						
						Commercial
						
						 | 
						Residential
					
					
								Material Suppliers Mechanic's Lien Information 
 for Residential projects 
Preliminary Notice Information (Pre-lien, 20 day Notice, etc.)
				| Notice Name | Required to secure future lien rights? | Timeframe information | 
| Preliminary Notice | Yes | 75 days from first furnishing labor or material if owner occupied OR the claim exceeds $10,000.00 | 
Mechanic's / Materialmen's Lien 
				| Notice of Intent Required? | Timeframe to file a Mechanic's / Materialmen's Lien | 
| No | 90 days after last providing material or labor | 