Preliminary Notice Information (Pre-lien, 20 day Notice, etc.)
Notice Name | Required to secure future lien rights? | Timeframe information |
Notice of Furnishing | Yes | 21 days from the start date OR 21 days from the filing of the Notice of Commencement |
Mechanic's / Materialmen's Lien
Notice of Intent Required? | Timeframe to file a Mechanic's / Materialmen's Lien |
No | 60 days after last providing material or labor |