Construction Resources | New Mexico
General Contractors
|
Subcontractors
|
Material Suppliers
Commercial
|
Residential
Material Suppliers Mechanic's Lien Information
for Residential projects
Preliminary Notice Information (Pre-lien, 20 day Notice, etc.)
Notice Name | Required to secure future lien rights? | Timeframe information |
Preliminary Notice | Yes | Prior to filing a lien and if any of the following is true: not in direct contract with the owner or prime contractor; claim will exceed $5,000.00; or the project is non-residential with less than 4 dwellings |
Mechanic's / Materialmen's Lien
Notice of Intent Required? | Timeframe to file a Mechanic's / Materialmen's Lien |
No | 90 days from completion of the project |
Disclaimer: Everything within this site is for informational purposes only; it is not and should not be considered legal advice. Be sure to consult with your construction law attorney to fully understand the Mechanic's Lien laws of your state and for your particular situation.